A new three-and-one system dares to make contractors’ jobs easier while reducing labor costs.
Michigan
contractors may be facing more-than-difficult hardships with a slowing housing
situation but seeking out building solutions with new products has given some
of these builders an edge. Case in point, Birmingham, Mich.-based general
contractor Mosher, Dolan, Cataldo & Kelly Commercial is about to wrap production
on a 32,000 square foot mixed-used building. The three-story complex, faced
with metal panels and masonry, will have an American Bistro on the first floor;
the second floor will be office space (and Mosher, Dolan, Cataldo & Kelly’s
new digs); and the third floor has 11 lofts, as well as covered parking.
The city of Birmingham is roughly 20 miles
northwest of downtown Detroit and is one of
several developing areas in Southeast Michigan.
As the city grows with commercial and institutional business, developers that
reside there are looking closer at sustainable building practices. Like other
metropolis areas, the city got a whiff of the loft boom and will surely
capitalize on it.
What marks this project as unique is that it is the first job in North America that will feature Dow’s new Total Wall
System. This system, for commercial steel stud wall assemblies, is designed to
achieve high energy efficiency, qualify for LEED certification and will
contribute to large energy savings. The system offers continuous insulation
value, air-barrier protection and a flashing system all-in-one. Dow says the
system, which incorporates its Thermax exterior sheathing, Stryofoam spray
polyurethane foam and Weathermate flashings, offers contractors ease of design
and installation. This advantage reduces construction time needed to install
the system, the bonus of less cost and labor.
The
irony is, Mosher, Dolan, Cataldo & Kelly had not originally specified the
system-it was not even aware that Dow was coming out with it.
“In watching many of the larger construction projects going on in metro
Detroit, like the casinos, we felt there was a better way to simplify the
details that the architects had come up with. Not only was it costly, it was subcontractor
specific so there was no multi-tasking among subcontractors and it didn’t
provide you with any quick construction methods,” says Steve Marszalek,
principal with Mosher, Dolan, Cataldo & Kelly. “We found out later also had
structural implications because it pushed the plane of your building out
farther than you wanted it to. So you had to increase your structural field
back to the building and it became a real vicious circle of trying to work
through all those details.”
ALTERNATIVES
The company had a meeting to discuss alternatives and it was suggested that the
company contact Dow since Mosher, Dolan, Cataldo & Kelly was going to use
its cavity-mate product on the project anyway. The call was placed to see if
Dow could provide a system that was a more simple system or “a way that we
could draw the envelope of the building back to where it belonged,” Marszalek
says.
Dow representatives had informed Mosher, Dolan, Cataldo & Kelly of a new
product that it offered that solved these concerns. Both companies spent three
months working through those details in refining the product, the Total Wall
System (not to be confused with the company of the same name).
The three-in-one package system benefits the contractors in many ways. For one,
it enables an energy-efficient, moisture-managed wall with less materials and
installation steps. Drywall contractor Dun-Rite worked on the project and used
this system. Its owner, Bruce Schihi, says the Total Wall System provides a
“better” exterior shell package with improved vapor and moisture seal. “The dew
point is moved to the exterior finish of the wall area, virtually eliminating
condensation behind the brick line.” He says the outcome is less labor and
material costs.
Typically, gypsum based wall systems begin with two men hanging board into
place, then installation of the foam, a basecoat of waterproofing membrane and
then a finish coat.
“When it’s done, you’re up to four trips around the building’s exterior,” says
Dun-Rite’s carpentry/drywall foreman Jerry Vanderpool. “Not only is Thermax
quicker to install, it’s really easy to use. I can cut it with a drywall
saw-and few cuts are needed since the 12-foot Thermax boards are longer than
gypsum boards, at 8 feet max. I can use fewer fasteners compared to exterior
gypsum-three screws per stud vs. about seven with gypsum. And one guy can
handle it easily … since it is so lightweight …”
He
continues to say that the overlap system of the company’s Thermax exterior
insulation has a shiplap edge of 1½ inch thickness and greater, which helps
hide imperfections that may be seen on the wall, providing a nice plane.
“It is a system because it’s done in conjunction with metal studs, insulation
and spray foam insulation on the interior for air migration,” says Marszalek.
“If you have the right carpenter, they can do all the functions: install the
studs, sheath the walls, install the brick ties and if certified also spray
foam the studs. So you have a total wall construction all done by one
contractor. From a construction manager’s standpoint … I now have the ability
to line up the next set of subcontractors to get immediately started. Now I
have a building that is safe, cost efficient to heat and it’s secure. And those
are values that you can’t even put a price on in the construction standpoint.”
This project also introduced contractors to the concept of blowing spray foam
insulation from the inside. Dow’s Styrofoam spray polyurethane foam, part of
the Total Wall System, was applied on the interior of the steel studs. In
theory, this will stop air infiltration by filling the gaps and penetrations,
and supply strong moisture management and elimination of air convection in the
wall. Jointly, the foam serves as insulation to the wall unit.
When asked what the cost for the system was compared to buying each of the
products piecemeal, Marszalek says it came out roughly the same to a
conventional gypsum-based system. The cost of turning a building over sooner
along with the energy costs to heat was substantial.
The project broke ground in April 2007 and is slated for completion by this
fall. When complete, the building will achieve USGBC LEED certification and a
Gold rating.
“I hope the product catches on,” says Marszalek. “It’s a product that makes
everybody’s lives easier-architects, builders, carpenters, etc.” W&C
It Comes in Threes
Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!