Reinforcement
products used to renovate a tarnished gem of a movie theater.
The landmark Olympia Theater and apartment building in Miami, a jewel of the
South Florida arts and cultural community since 1926, was recently in a state
of massive deterioration and disrepair. The historic 10-story high-rise complex
was facing an uncertain future. Serious discussions would be required if an
emergency and long-term repair solution wasn’t developed to address pressing
structural and safety issues surrounding the building’s exterior brick masonry
cladding and terra cotta façade.
A concerted $2.1 million restoration effort by the City of Miami and the Miami
Parking Authority (which runs the theater) began when historic preservation and
architecture design firm, R.J. Heisenbottle Architects, P.A. of Coral Gables,
Fla. was brought in to head the restoration effort. RJHA President Richard
Heisenbottle immediately consulted with the interdisciplinary structural
engineering and architectural firm Wiss, Janney, Elstner Associates, Inc. of
Northbrook, Ill. to conduct an initial onsite assessment.
The preliminary assessment was performed over two days in late October 2009 to
investigate the buildings distresses and design an emergency stabilization
procedure before installation of long-term repairs for the exterior masonry
cladding could occur. WJE collaborated with industry leading masonry repair
reinforcement system manufacturer Helifix Inc. of Streetsboro, Ohio to provide
a supplementary and sustainable lateral and gravity support system for the
building’s distressed veneer using its Helibeam System.
HOW
THAT WORKS
The key focus of the Helibeam System was the use of stainless steel (austenitic
grade 304 or 316) HeliBars seven meters long to create a reinforced beam across
each spandrel level to distribute and support the structural loads across the
piers and into the steel lintels and spandrel beams.
HeliBar starts as round stainless steel wire with a typical 0.2 percent proof
stress of 500N/mm². After the cold forming manufacturing process that creates
the helical hi-fin design, the proof stress doubles to approximately 1100N/mm².
This means that HeliBar, with its relatively small diameter, provides
substantial tensile strength to masonry, particularly when combined with
HeliBond grout which locks between the fins and bonds to the masonry.
Rounding out the Helibeam System, approximately 9,000 10 millimeter DryFix
remedial ties were installed through the veneer and into the backup-providing
lateral restraint and securing the façade.
SAVE BUILDINGS
According to WJE Associate Principal Brett Laureys, “The Helibeam System was
specified because of its proven ability to secure existing masonry. It is fully
concealed (once installed) and its flexibility allows it to be bent around
corners with no loss of performance. It was also the most cost-effective
stabilization method available and, with all work undertaken externally, there
was minimal disruption to the upper floor tenants during this emergency
restoration phase which overcame the veneer’s lack of support, securing the
structure while full renovation of the Olympia Theatre was safely
undertaken.”<
THE
PROCESS
In conjunction with Helifix’s on-site quality control and assurance support
team, installation of the Helibeam System at the Olympia Theater was conducted
by industry leading specialty repair contracting company Structural
Preservation Systems of Hanover, Md. To form the Helibeam System, two
horizontal rows of 7-meter long stainless steel HeliBars were laid at various
levels around the circumference of the building. This creates a deep masonry
beam to distribute the structural load and provide gravitational support around
the entire building.
Installation involved cutting out 1¾-inch deep slots in the mortar joints which
were vacuumed and then flushed with water. A bead of thixotropic cementitious
HeliBond grout was laid in and the 7-meter length of HeliBar was then placed in
the slot. The grout-HeliBar-grout process was repeated on top to complete the
composite action of the Helibeam System. When each length of HeliBar came to
its end, the next length was overlapped to create one monolithic run around the
building with corners kinked in at a 90-degree bend. The recessed Helibeam was
then pointed over the top, rendering it virtually transparent to the naked eye
upon completion.
Additionally, DryFix remedial ties used in tandem with Helibeam System for
lateral restraint in the façade. The DryFix ties were installed by being
power-driven into position via a small pilot hole using a special installation
tool that leaves the end of the tie recessed below the outer face-allowing an
invisible finish. Crack stitching was also conducted to secure local cracking
and stabilize any further movement of separating brick areas. According to SPS
Project Engineer/Manager Alan Fleischer, “The Helibeam installation was easy,
as it’s a lot like crack stitching but in a longer run. After we completed the
installation, you’d never know what was done to the
building.”
THE RESULTS
The Helibeam System was installed within four months of WJE’s specification
beginning with the anchors and completed in August 2010. An alternative to
complete structural tear down and rebuild, the system delivered an efficient
green solution in restoring the historic Olympia Theater. According to Helifix
VP for North American Operations Reno Fricano, “Ultimately, in collaborating
with WJE and SPS throughout the entire specification, design, and installation
phases, the system provided a non-invasive, cost-effective, and sustainable
stabilization solution in revitalizing the architectural luster and integrity
to one of America’s original movie palaces.”
WJE’s Brett Laureys says, “The repairs were successfully installed, meeting the
client’s needs of an emergency stabilization method which could be installed
immediately, quickly, and inexpensively. It’s hard to compare with it as it was
more cost effective than traditional stainless steel threaded rod and
epoxy.”
Finally, RJHA’s Heisenbottle noted, “The initial emergency (Phase I)
restoration looks beautiful and the team is proceeding with the final (Phase
II) $10 million restoration of the theater side of the building and the terra
cotta tower which should round out the project sometime in 2012.”
Picture Perfect
Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!